On ground-mount solar plants the pile is a steel profile driven directly into the ground instead of a concrete footing. Embedment depth determines the cost of the table, the speed of installation and the structural safety of the plant over a 25–30-year design life. There is no single depth valid for every site; it is set by ground conditions, design loads and load tests on site.
Summary: on fixed-tilt systems embedment lies between 1.2 and 2.5 m on many sites; ground with lower bearing capacity needs more and rocky ground needs pre-drilling. Geotechnical design follows EN 1997-1 (Eurocode 7) or the local code governing the project. The process for setting the depth is described step by step below.
Loads on the pile: uplift, lateral load and compression
Uplift: wind suction on the back of the modules tries to pull the pile out of the ground. On light solar tables this is often the governing load, resisted by skin friction along the pile.
Lateral load and moment: the horizontal wind component creates a moment at the pile head, which the soil resists laterally. The longer the pile above ground, the larger the moment at ground level.
Compression: the self-weight of table and modules plus snow push the pile down; on most soils this governs less than uplift and lateral load.
Design loads are derived from EN 1991-1-4 for wind and EN 1991-1-3 for snow (or ASCE 7); because wind pressures are higher at array edges and corners, edge piles see higher uplift and moment than interior ones.
Step 1 — Geotechnical survey and soil zones
Boreholes and trial pits across the site establish the soil layers, density (e.g. SPT values), stone and boulder content, groundwater level and the soil's corrosive properties (resistivity, pH, chlorides, sulphates). Distinct soil zones are mapped; each may need its own pile depth. The corrosive properties also determine the coating class — see our Zn-Al-Mg guide.
Step 2 — Test piles and load testing
At representative points chosen from the survey, test piles of the production section are driven to the planned depths. A hydraulic jack applies load in increments; force is recorded with a load cell and displacement with dial gauges or displacement transducers, and a load–displacement curve is reported for each test. The test procedure is defined in the project specification; international projects frequently reference ASTM D3689 (axial tension), ASTM D3966 (lateral load) and ASTM D1143 (axial compression). A typical programme covers three load cases:
| Test | Procedure | Evaluation |
|---|---|---|
| Axial pull-out | The pile is pulled upward in load steps | At the design uplift the allowed displacement must not be exceeded |
| Lateral load | A horizontal force is applied at the pile head | Horizontal head displacement is measured against the limit value |
| Compression | Vertical loading where the site calls for it | Vertical displacement and capacity are verified |
The designer sets the acceptance criteria and the number of tests; the results feed back into the structural calculation to fix pile depth and section for each soil zone. On Y Solar projects the pull-out test results form part of the delivery documentation, together with the static report and installation drawings.
Step 3 — Driving, refusal and pre-drilling
Piles are installed with hydraulic pile drivers, often GPS-guided. The main tolerances checked on site are verticality, head level and row alignment; the adjustment slots in the connections are designed to absorb them.
When a pile stops advancing before design depth, this is termed refusal. The pile should not be forced: it can be driven into a pre-drilled hole, the soil zone can be re-assessed, or rocky areas can switch to an alternative foundation such as ground screws or concrete footings. A thin-walled pile forced into hard ground can suffer tip damage and loss of coating.
Optimising section and depth together
A stiffer section — a larger C-pile or a sigma pile — deflects less under lateral load; driving deeper raises uplift capacity but adds length and tonnage. The most economical solution comes from optimising section and depth together in a structural calculation calibrated by the test results, with cold-formed sections verified to EN 1993-1-3.
Tracker posts, carrying the dynamic wind loads of a rotating table, are usually larger in section and deeper than fixed-tilt piles — see W-beam piles.
Site checklist
Before pile driving starts, confirm that each of the following is in place.
| Item | Check |
|---|---|
| Geotechnical survey | Are the survey report and soil-zone map complete? |
| Load tests | Have pull-out and lateral tests been run for every soil zone and fed into the calculation? |
| Design | Are design depth, pile length and section fixed for each zone? |
| Refusal procedure | Is the refusal procedure (pre-drilling, alternative foundation) defined? |
| Tolerances | Do driving tolerances match the connection slot lengths? |
| Coating repair | Are the coating repair method and materials available on site? |
